Sunset Boulevard esplanade plan puts 445 mangroves on the line

Google Earth Pro screengrab shows the proposed alignment of the esplanade project in Barangay Sooc, Arevalo District, based on the project layout plan DPWH-6 submitted to CENRO (inset).
By Rjay Zuriaga Castor
ILOILO CITY — A proposed esplanade in Barangay Sooc, Arevalo District, could directly affect about 445 mangroves, prompting the City Environment and Natural Resources Office (CENRO) to oppose the project and call for further review.
The esplanade is part of the Iloilo River North Bank Road project.
In an inspection and recommendation report obtained by Daily Guardian, CENRO said the esplanade segment directly traverses an established mangrove-dominated ecosystem, putting mature trees and naturally regenerating saplings at risk.
The Iloilo River North Bank Road, also known as Sunset Boulevard, is a roughly five-kilometer, four-lane Department of Public Works and Highways (DPWH) road connecting Barangay Tabucan in Mandurriao, Iloilo City, to Barangay Cagbang in Oton, Iloilo.
The PHP 2.261-billion road officially opened to the public Jan. 24, 2025.
In January, DPWH said it was targeting completion of civil works by the third quarter of 2026, with unpaid right-of-way claims remaining a major challenge.
The esplanade will include five viewing decks, according to the project layout plan that DPWH Western Visayas (DPWH-6) submitted to CENRO.
Daily Guardian’s mapping of the proposed alignment on Google Earth Pro showed that the section spans about 1.5 kilometers.
DPWH-6 asked CENRO three times between September 2025 and September 2026 for a Certificate of No Objection (CNO) in connection with the earth-balling and tree-cutting permits required for construction.
A CNO is a formal clearance showing that CENRO raises no environmental or community opposition to a proposed activity or project.
Based on a joint mangrove and tree inventory conducted July 30 and Aug. 6, CENRO reported that road filling, clearing, and embankment works could directly affect about 445 mature mangroves and naturally regenerating saplings.
CENRO described the project site as a highly sensitive ecological zone that provides important environmental functions within the Iloilo River and its adjoining coastal environment.
“The proposed [project] must not result in the irreversible degradation or destruction of an established mangrove ecosystem, particularly one that serves as a natural coastal defense system and an important component of the city’s remaining urban biodiversity,” CENRO said.
“While the push for infrastructure development in Iloilo City is a recognized driver of economic progress, the proposed [project] must not come at the cost of irreversible ecological damage. The proposed project is inherently incompatible with the site’s environmental realities,” it added.
CENRO warned that conventional road construction involving earth filling, embankment development, and site preparation could permanently destroy and fragment mangrove habitats, disrupt tidal flows, increase sedimentation, and disturb aquatic organisms.
It said the ecological value of the affected area cannot be measured solely by the number of trees that may be removed.
“Consequently, replacing the affected trees through compensatory planting in another location would not immediately restore the ecological functions of an established mangrove ecosystem,” CENRO said.
Those functions depend on interconnected vegetation, root systems, soil conditions, tidal circulation, and aquatic habitats, the office added.
CENRO also said the proposed alignment falls within an area protected under the Iloilo City Coastal Greenbelt Ordinance, which took effect in July.
The City Council unanimously approved the measure, authored by Councilor Romel Duron, on July 1. It also bans coastal reclamation.
The ordinance establishes a mandatory 100-meter coastal buffer zone across 32 coastal barangays and protects roughly 100 to 110 hectares of mangrove forests.
CENRO said the area’s inclusion in the coastal greenbelt raises legal and regulatory concerns, particularly if construction would require the unauthorized cutting, removal, or destruction of mangroves.
It recommended that DPWH establish the project’s compatibility with the ordinance and secure all necessary permits, clearances, and approvals before undertaking construction that could affect the mangrove ecosystem.
Comprehensive review pushed
CENRO called for a comprehensive assessment that would include georeferenced mapping of the mangroves and project footprint, verification of the 445 potentially affected trees, evaluation of impacts on tidal circulation and biodiversity, and examination of alternative road alignments and engineering designs.
It said the project design should prioritize preserving existing mature mangroves and naturally regenerating vegetation instead of relying on compensatory planting to offset the loss of an established ecosystem.
“The principle of avoidance should be given priority over mitigation and compensation, consistent with the mitigation hierarchy in environmental planning,” it said.
Pending completion of the assessments, the office recommended that no clearing, tree cutting, earth filling, excavation, or other construction activities affecting the mangroves be undertaken.
CENRO also urged the City Council to consider passing a resolution recognizing and recommending the designation of the Sooc mangrove area as a Local Mangrove Conservation and Natural Heritage Site.
A CNO from CENRO will serve as the City Council’s basis for passing a Resolution of No Objection for the project.
“The protection of the Sooc mangrove area is not an impediment to development; rather, it is an investment in the long-term environmental security, ecological integrity, and sustainable future of Iloilo City,” CENRO said.
Comments (0)
LEAVE A REPLY
No comments yet
Be the first to share your thoughts!
Related Articles

G2G ARRANGEMENT: NIA, MIWD tap Jalaur for Metro Iloilo water supply
ILOILO CITY — The National Irrigation Administration and the Metro Iloilo Water District are working to develop the bulk water component of the Jalaur River Multi-Purpose Project Stage II, Iloilo’s biggest irrigation development project. The government-to-government arrangement aims to maximize the resources of both agencies in developing the component’s infrastructure, policy, financial,

Metro Pacific Water: Resilience in Every Drop
El Niño tests more than the amount of water available in reservoirs, rivers and aquifers. It tests whether water systems can endure prolonged dry conditions and keep water flowing reliably to communities as supplies come under pressure. For Metro Pacific Water (MPW), a subsidiary of Metro Pacific Investments Corp. (MPIC), resilience means preparing before households

Primelectric backs resilient power supply deals at PHILRECA 2026
CEBU CITY — Primelectric Holdings Inc. (PHI) pushed for resilient power supply agreements amid an unpredictable energy market during a recent gathering of electric cooperatives at the Waterfront Cebu Hotel. PHI participated in the Philippine Rural Electric Cooperatives Association (PHILRECA) event, which brought together industry leaders and stakeholders to discuss