G2G ARRANGEMENT: NIA, MIWD tap Jalaur for Metro Iloilo water supply
By Steve Cordero

ILOILO CITY — The National Irrigation Administration and the Metro Iloilo Water District are working to develop the bulk water component of the Jalaur River Multi-Purpose Project Stage II, Iloilo’s biggest irrigation development project.
The government-to-government arrangement aims to maximize the resources of both agencies in developing the component’s infrastructure, policy, financial, and institutional arrangements.
Both are government-owned and controlled corporations involved in water resource development, with NIA handling irrigation and MIWD handling municipal and domestic water.
Under the arrangement, MIWD will develop 1 cubic meter of water per second, or 86.4 million liters per day, from JRMP II for bulk water purposes.
NIA said the allocation will not affect irrigation water delivery.
Supply targeted by 2028
NIA will build a take-off point at the High Line Canal section in Barangay Gaub in the town of Cabatuan.
MIWD will connect its transmission lines to that point and draw its allocated water.
The arrangement covers a 25-year supply period that will begin once NIA’s High Line Canal section and MIWD’s transmission lines and water treatment facility are completed and operating.
All of these facilities are targeted for 2028.
The bulk water component is expected to help MIWD address Metro Iloilo’s demand gap of 153 million liters per day.
It is also expected to stabilize supply for current customers, especially in Iloilo City.
MIWD likewise aims to expand service to unserved households in seven municipalities: Oton, Santa Barbara, Cabatuan, Maasin, San Miguel, Pavia, and Leganes.
Less reliance on groundwater
The additional supply is also expected to limit Metro Iloilo’s reliance on groundwater, especially during the dry season.
This would reduce adverse effects on the water table, including saltwater intrusion and land subsidence, according to NIA.
NIA and MIWD signed the government-to-government agreement April 22 following what NIA described as rigorous due diligence.
The Asian Development Bank’s Transaction Advisory Services assisted NIA in that process.
The Office of the Government Corporate Counsel and the Public-Private Partnership Center also reviewed the arrangement.
NIA said the bulk water component shows how JRMP II delivers wide-ranging benefits and fuels growth across Iloilo and Western Visayas.
The agency added that the project, true to its slogan “Katuwang sa Kauswagan,” remains timely and much needed for every Ilonggo family.
Project background
NIA and MIWD signed a memorandum of understanding July 29, 2025, allowing the water district to conduct a one-year feasibility study on sourcing water from JRMP II.
MIWD is the joint venture partner of Metro Pacific Iloilo Water.
President Ferdinand Marcos Jr. inaugurated the project’s three dams in Calinog on July 16, 2024, although work continued on canals and other irrigation components.
As of September, the project was 87.92% complete, while its irrigation component was about 50% complete.
NIA has said JRMP II is on track for completion by the end of 2027, with full operations expected in 2028.
Comments (0)
LEAVE A REPLY
No comments yet
Be the first to share your thoughts!
Related Articles

Metro Pacific Water: Resilience in Every Drop
El Niño tests more than the amount of water available in reservoirs, rivers and aquifers. It tests whether water systems can endure prolonged dry conditions and keep water flowing reliably to communities as supplies come under pressure. For Metro Pacific Water (MPW), a subsidiary of Metro Pacific Investments Corp. (MPIC), resilience means preparing before households

Primelectric backs resilient power supply deals at PHILRECA 2026
CEBU CITY — Primelectric Holdings Inc. (PHI) pushed for resilient power supply agreements amid an unpredictable energy market during a recent gathering of electric cooperatives at the Waterfront Cebu Hotel. PHI participated in the Philippine Rural Electric Cooperatives Association (PHILRECA) event, which brought together industry leaders and stakeholders to discuss

Sunset Boulevard esplanade plan puts 445 mangroves on the line
ILOILO CITY — A proposed esplanade in Barangay Sooc, Arevalo District, could directly affect about 445 mangroves, prompting the City Environment and Natural Resources Office (CENRO) to oppose the project and call for further review. The esplanade is part of the Iloilo River North Bank Road project. In an inspection and