Power partially restored in Negros Occidental town
BACOLOD City – The Northern Negros Electric Cooperative (Noneco) has partially restored the power in E.B. Magalona, Negros Occidental on Saturday morning, following a four-day blackout due to the tripping of the 15 MVA power transformer in Victorias City substation in Negros Occidental. The power outage since August 29 also affected the

By Glazyl Masculino

By Glazyl Masculino
BACOLOD City – The Northern Negros Electric Cooperative (Noneco) has partially restored the power in E.B. Magalona, Negros Occidental on Saturday morning, following a four-day blackout due to the tripping of the 15 MVA power transformer in Victorias City substation in Negros Occidental.
The power outage since August 29 also affected the neighboring city of Victorias and a portion of Manapla town.
In an advisory by Noneco on September 2, the power firm said that partial power restoration was implemented at 3 a.m. in E.B. Magalona town.
However, the town is still experiencing some power interruptions, as Noneco is still balancing the power load to prevent overloading of power lines with the Central Negros Electric Cooperative (Ceneco).
On August 31, Noneco linemen constructed lines to interconnect with Ceneco lines to temporarily restore power in the area of E.B. Magalona town, as one of the power firm’s solutions, while repairing the power transformer in Victorias City.
Noneco sought the assistance of Ceneco to provide a temporary remedy for the power crisis in the third district of the province.
Victorias City Mayor Javi Benitez, earlier said that Ceneco loaned Noneco a 15MVA transformer stationed at the CyberCentre here to restore power in the said city.
On Saturday night, Noneco said that Ceneco’s power transformer arrived at the Noneco Bacayan, Victorias substation to replace Noneco’s broken transformer.
Benitez said yesterday that the transformer successfully cleared all nine required tests: oil dielectric strength, TTR (primary to secondary), insulation resistance and P.I., winding resistance, overall insulation power factor, bushing hot collar, excitation current, impedance, and grounding (earth) resistance.
At 1:33 p.m. yesterday, Noneco submitted the test results to the National Grid Corporation of the Philippines (NGCP) for approval.
NGCP will conduct tripping simulations to confirm that all installed protections are operational, Benitez said.
Upon approval, Noneco will begin the commissioning and electrification process, he added.
Power is expected to be fully restored to Victorias, E.B. Magalona, and Manapla after these processes, Benitez said.
Article Information
Comments (0)
LEAVE A REPLY
No comments yet
Be the first to share your thoughts!
Related Articles
DENR pushes 2027 deadline for new Iloilo bulk water supply
A top official of the Department of Environment and Natural Resources said Iloilo must have a new bulk water supply operational by 2027, warning that the city’s rapid urban growth will further increase water demand in the coming years. Carlos Primo David, DENR undersecretary for integrated environmental science and head of

Treñas-Chu slams MPIW over permit delay claims
Iloilo City Mayor Raisa Treñas-Chu criticized Metro Pacific Iloilo Water on Thursday for what she described as the company’s failure to directly raise concerns about alleged delays in the processing of permits for its desalination plant project in Barangay Ingore, La Paz. “I would have appreciated it if MPIW had informed