Igbaras mayor denies ghost projects, says P16.3M funds remained untouched
By Rjay Zuriaga Castor

ILOILO CITY – Igbaras Mayor Vicente E. “Juvic” Escorpion has denied allegations of ghost projects, saying PHP 16.377 million allocated for 42 unimplemented projects flagged by the Commission on Audit (COA) remained unspent before being reprogrammed for other development initiatives.
In a statement on Saturday, Nov. 14, Escorpion said his administration realigned the appropriations earlier this year following recommendations from the Municipal Development Council and approval by the Sangguniang Bayan.
He said projects funded through the realigned appropriations are now being implemented, while others are scheduled to start soon.
COA reported that the 42 infrastructure and social service projects, funded through the municipality’s 20% Development Fund from 2016 to 2022, remained unimplemented as of Dec. 31, 2025.
The audit found that the PHP 16.377 million in appropriations had remained idle at the end of 2025 because the projects had neither been implemented nor the funds reprogrammed.
“The 42 alleged unimplemented projects are difficult, if not impossible, to implement,” Escorpion said.
The mayor said allocations of PHP 100,000 to PHP 125,000 for each of the municipality’s 46 barangays were insufficient to complete the proposed projects.
Despite his reminders and warnings about the need to realign the funds, he said the barangays failed to use their respective allocations.
Escorpion said the funding arrangement covering the projects was implemented between 2020 and 2022, when he was no longer mayor.
He served as mayor from 2010 to 2019 and returned to the position in 2022.
Jaime E. Esmeralda served as mayor from 2019 to 2022.
Escorpion said unimplemented projects do not automatically constitute ghost projects, arguing that the distinction depends on whether public funds were spent despite the absence of actual implementation.
“Granting for the sake of argument that there [are] unimplemented [projects], still the budget is untouched. If the budget is utilized or expended, but the project does not exist, then there is a ghost project,” he said.
“The present case is different. [The projects remained] unimplemented for valid reasons, [their] budgets [were] reprogrammed [for] other projects, [and the] new projects [are now being] implemented,” he added.
He urged the public to understand the circumstances behind the unimplemented projects and avoid unfounded concerns.
COA identified insufficient funding for individual projects as the primary reason for the delays.
It said the allocations for specific barangay projects were too small to cover the cost of constructing or repairing the proposed facilities.
Most of the stalled projects involved barangay infrastructure, including road concreting, health centers, and multipurpose buildings.
COA also noted that barangay captains were unable to initiate or request the proposed works because the funds allocated to their respective barangays were insufficient.
Comments (0)
LEAVE A REPLY
No comments yet
Be the first to share your thoughts!
Related Articles

‘DAPAT ISA LANG’: 11 groups urge Filipinos to sign anti-dynasty people’s initiative
Eleven business, legal, civic, and church-based organizations have urged Filipinos to sign the Dapat Isa Lang People’s Initiative, a citizen-led push to enact an anti-political dynasty law. In a joint statement dated Nov. 4, the groups asked the public to visit d1l.org, read the proposed Anti-Political Dynasty Act, and sign

Scientists, communities to map who El Niño will hit hardest
QUEZON CITY — The University of the Philippines (UP) and the Natural Resources Development Corporation (NRDC) will convene a national consultation on El Niño on Nov. 20 and 21 to produce a response action matrix for submission to President Ferdinand R. Marcos Jr. The National Multi-Stakeholder Consultation on El Niño

‘ALL TALK ON BUDGET REFORMS’: Budget watchdog seeks written House pledge to open 2027 bicam
By Joseph Bernard A. Marzan ILOILO CITY — The People’s Budget Coalition (PBC) said the House of Representatives has yet to turn its promises to reform the 2027 national budget into concrete action, particularly a written guarantee that civil society groups and media can attend bicameral conference committee deliberations in person. At a virtual press