Three heritage buildings crumbling, up for probe
The Iloilo City government said three buildings in the downtown heritage zone will be investigated by experts for possible structural problems. A May 4, 2023 report submitted to Iloilo City Mayor Jerry Treñas on May 10, Office of the Building Official (OBO) chief Mavi Gustilo indicated that the Locsin-Coscuella, John A.

By Joseph B.A. Marzan

By Joseph B.A. Marzan
The Iloilo City government said three buildings in the downtown heritage zone will be investigated by experts for possible structural problems.
A May 4, 2023 report submitted to Iloilo City Mayor Jerry Treñas on May 10, Office of the Building Official (OBO) chief Mavi Gustilo indicated that the Locsin-Coscuella, John A. Tan, and the S. Villanueva (or Atmer) buildings must be investigated by a structural engineer to be hired by the building owners.
The Locsin-Coscuella Building at the corner of Iznart and Ledesma streets was observed to have suffered exposed and corroded reinforced steel bars, presence of wide and deep concrete cracks, presence of water leak marks, exposed unorganized electrical wiring, and multiple tapping or octopus connections. This building is already which is 103 years old.
Another 2 units of the building occupied by a bicycle shop, were also found with rusted steel frames and broken glass, deteriorated concrete moldings, dilapidated steel signage, and loose, tangled, and exposed wires and cables.
Defects in the John A. Tan building, which was constructed in 1958, included concrete cracks, exposed corroded rebars, deflection and vibration in a concrete slab on the second floor, deteriorated ceiling, piled stocks of supplies, loose and tangled wires, no entrance cap, broken circuit protections, and undersized feeder wires.
The S. Villanueva building has horizontal connection cracks, significant vertical cracks with concrete bulging, and rainwater leakage at the right side firewall coming from the inside gutter.
Gustilo said in her cover letter that the investigation’s results would lead to further actions that must be undertaken by the owners.
“The result of the structural investigation will serve as the reference for the recommendations on whether the building needs to be repaired, retrofitted, or demolished,” she said in her letter.
HAZARDS?
The OBO chief also discussed with the media the dangers of the defects observed from their assessments.
Without saying it directly, Gustilo implied that the crumbling building might pose threats to public safety, particularly to pedestrians passing by the areas.
“There were concrete columns with cracks, which are now major cracks, their steel bars as reinforcements now exposed and corroded, and in their major structural component beams, those are also showing cracks,” Gustilo explained.
“There were also water leaks, and once they are visible, that means that they have seeped in through and through. For example, if the beam has a water leakage, that’s already through and through, which is dangerous,” she added.
A total of 35 buildings were inspected by the OBO located in Iznart, Ledesma, Aldeguer, J.M. Basa, Arroyo, and Arsenal streets in the downtown central business area.
These visual assessments were conducted after reports by the media of broken glass falling from the windows of the Locsin-Coscuella Building earlier this month.
Article Information
Comments (0)
LEAVE A REPLY
No comments yet
Be the first to share your thoughts!
Related Articles
DENR pushes 2027 deadline for new Iloilo bulk water supply
A top official of the Department of Environment and Natural Resources said Iloilo must have a new bulk water supply operational by 2027, warning that the city’s rapid urban growth will further increase water demand in the coming years. Carlos Primo David, DENR undersecretary for integrated environmental science and head of

Treñas-Chu slams MPIW over permit delay claims
Iloilo City Mayor Raisa Treñas-Chu criticized Metro Pacific Iloilo Water on Thursday for what she described as the company’s failure to directly raise concerns about alleged delays in the processing of permits for its desalination plant project in Barangay Ingore, La Paz. “I would have appreciated it if MPIW had informed