Panay’s 2024 blackout explains Pax Silica’s biggest problem
By Francis Allan L. Angelo
Ilonggos opened the first workweek of 2024 in the dark, after power plants on Panay tripped one after another on January 2 and the island did not fully recover until January 5.
Those four days explain the weakest point of Pax Silica, the US-led plan to build a 4,000-acre technology hub in New Clark City, Tarlac, better than any diplomatic communique.
The deal will not be won or lost on sovereignty or on investor brochures, but on electricity and on whether Filipinos get to do more than assemble other countries’ chips.
That is the core of a policy brief published August 4 by the Pacific Forum, written by Rafael Munoz, a Philippine Army officer and graduate researcher at the University of Hawai’i Economic Research Organization.
It is also the argument we would put on the desk of President Ferdinand Marcos Jr., where the Bases Conversion and Development Authority (BCDA) sent its recommended framework agreement in October.
Start with what is settled. Reports had Washington seeking diplomatic immunity and even US jurisdiction over the zone, claims that Under Secretary of State Jacob Helberg later said were taken out of context.
BCDA President Joshua Bingcang ruled out immunity and kept the hub inside the existing special economic zone framework under Republic Act 7916 and the BCDA charter, RA 7227.
In short, the flag question has been answered, and Manila answered it.
The power question has not, as Munoz writes that the industrial zone alone is expected to need 5,000 megawatts of generating capacity.
The Luzon grid peaks at roughly 13,000 to 14,000 megawatts, so a single estate would add 35 to 40 percent to the island’s peak demand.
Philippine industrial power cost USD 0.1474 per kilowatt-hour in early 2026, about PHP 8.90 at the brief’s exchange rate and roughly 34.8 percent above Vietnam’s USD 0.1093.
Fossil fuels generate 75.21 percent of the country’s electricity, which leaves every factory and every household exposed to price shocks like those that followed the recent Middle East conflicts.
The National Grid Corporation of the Philippines (NGCP), the same operator lawmakers grilled over the Panay blackout, is 40 percent owned by China’s State Grid Corporation.
Munoz draws the obvious conclusion that allied investors will hesitate to build a supply chain meant to reduce reliance on China on a grid that a Chinese state firm partly owns.
Here the documents do not agree with each other. Bingcang has said the hub will not host data centers and will be predominantly industrial, which would shrink the power requirement considerably if it holds.
Munoz’s 5,000-megawatt estimate is framed around advanced chip packaging and AI data centers, and the Department of Trade and Industry has said such facilities may still rise wherever power and water allow.
So we ask the BCDA plainly: how many megawatts will the hub actually draw, from which plants, and on whose bill?
The second problem is the smiley curve, an economist’s way of saying that assembly employs the most people and keeps the least money.
The Philippines already holds an edge in semiconductor assembly, testing, and packaging, and the presence of Foxconn Chairman Young Liu during Helberg’s May visit showed where the first real investment will come from.
That is genuine momentum, but it is momentum toward the low-margin floor of the factory.
The BCDA projects 130,000 to 190,000 direct jobs, and the country needs every one of them.
Jobs at the bottom of the curve, however, will not make the Philippines the processor of its own critical minerals or the designer of its own chips.
Supporters will say we are asking a project that Bingcang himself says could take 30 years to prove itself before it breaks ground, and that is a fair point.
The Management Association of the Philippines has backed what it calls a “Proceed, but Protected” approach, and we share the instinct.
Protection, though, has to be written into the framework, not recited at press briefings.
Before the President signs, the agreement should state where the hub’s power will come from, who pays for it, and how much of it stays off the grid that ordinary consumers share.
The BCDA’s 500-megawatt solar-plus-storage project with Acwa, a Saudi Arabian firm, is a start, though Munoz concedes that projects of that scale meet only a portion of the need.
The framework should also commit both governments to timelines for processing local critical minerals under local ownership and for technology transfer, the route Taiwan took up the curve.
Senators weighing whether the deal needs their concurrence should ask for those numbers first.
Iloilo knows what an energy promise is worth before the wires are strung. Ask anyone in Panay.
Comments (0)
LEAVE A REPLY
No comments yet
Be the first to share your thoughts!
Related Articles

Trapped in the feed
THIRTY-THREE hours and 50 minutes a week. That is how long the average Filipino spends on social media, according to the Digital 2026 Philippines report by Meltwater and We Are Social. The global average, per the two companies’ Digital 2027 report released Oct. 21, is 19 hours and 18 minutes. In short, the country has

InkSights: question power, but check your facts
Give young journalists a politician, a school building, and an oversized smiling face on a tarpaulin, and you will rarely have to wait long for an opinion. That became wonderfully clear during our recent InkSights Unscripted journalism masterclass in Iloilo City. The editorial writers were asked to wrestle with politicians putting

Dynastic rule, a facade of democracy, poverty and the media
Behind the facade of Philippine democracy lies a deeply entrenched oligarchy created during the Spanish and American colonial eras. An elite group of powerful families now rules the country after consolidating their influence through their control of Congress and mainstream media. Political power rests not in winning the popular vote, but