MORE Power completes 69kV line transfer at ISAT-U
A request by Iloilo Science and Technology University (ISAT-U) in LaPaz, Iloilo City that remained in the doldrums for two years became a top priority for MORE Electric and Power Corp. The construction of an overpass linking the two campuses of ISAT-U on Burgos Street, LaPaz was put on

By Francis Allan L. Angelo

By Francis Allan L. Angelo
A request by Iloilo Science and Technology University (ISAT-U) in LaPaz, Iloilo City that remained in the doldrums for two years became a top priority for MORE Electric and Power Corp.
The construction of an overpass linking the two campuses of ISAT-U on Burgos Street, LaPaz was put on hold while waiting for the 69-kV power line to be relocated by the previous distribution utility.
The school’s request for the transfer of the line came to fruition on Sunday as engineers and linemen of MORE Power relocated the high-voltage wires to a higher electric pole.
The relocation coincided with the corrective and preventive maintenance works on the Mandurriao Substation on the same day.
“MORE installed an intermediate pole in order to clear, as per the school’s request, an overpass bridge that crosses the highway and links their two campuses. They had been requesting PECO non-stop for this work to be done for years but it remained a problem until we came along,” said Engr. Paterno Cabangisan, MORE Power’s Head of Transmission Lines.
No less than MORE Power president Roel Castro, together with ISAT-U officials, supervised the relocation of the 69kV line that took about six hours.
“It entailed a little inconvenience on the part of our consumers—our apologies–but the safety of ISAT-U students is imperative. And we had to do this on the least interruptive day. Buti na lang the consumers understood why this had to be done,” Castro said.
ISAT-U officials said they were glad to see MORE Power workers relocate the 69kV line to an 80-foot intermediate pole in the area.
“I am very, very happy that after two long years, it’s finally done. At long last, we can proceed with our overpass project,” Russ Allen Napud, ISAT-U Director for Planning Development and Auxiliary Services, said.
“Actually, the entire University is very happy. Construction of the skywalk started in 2017 but had to stop the next year because of the 69kV line. We requested PECO to help us relocate the line, but they did nothing. Now we are extremely glad that this was carried out with the help of MORE Power. We are all looking forward to the completion of this project very soon,” according to Engr. Gabriel Salistre, Jr., ISAT-U Vice President for Administration and Finance.
“On behalf of the University, we would like to say ‘thank you’ from the bottom of our hearts to MORE Power for realizing the transfer of that 69kV line to a much safer place. Now, there’s nothing that prevents us from completing the overpass,” Napud added.
Once completed, the access route for the two campuses will be a big help to students, teachers, stakeholders, and officials, providing them with a much safer and more convenient access between the two campus sites.
In an earlier interview, ISAT-U president Dr. Raul Muyong expressed his gratitude to MORE Power president Roel Castro for acting on the problem with speed.
“In fact, MORE Power visited the site as soon as they received our request to evaluate the situation. They also promptly submitted a proposal to correct the problem, which we agreed with,” he said.
“We are grateful because it will now be very easy for us to access the other side of the campus,” he said.
Muyong recalled that MORE Power’s quick action was a far cry from what the previous distribution utility’s response when the problem was brought to the attention of the former utility distributor.
“We had formal communications with PECO and even signed a certificate of undertaking with them regarding the problem. We also solicited the help of local officials to help us appeal to PECO to address our concerns, but all those requests fell on deaf ears,” he noted.
He added that the school ended up purchasing high voltage conductor covers to ensure the safety of the personnel working on the access route while they were waiting for PECO’s action.
Article Information
Comments (0)
LEAVE A REPLY
No comments yet
Be the first to share your thoughts!
Related Articles
DENR pushes 2027 deadline for new Iloilo bulk water supply
A top official of the Department of Environment and Natural Resources said Iloilo must have a new bulk water supply operational by 2027, warning that the city’s rapid urban growth will further increase water demand in the coming years. Carlos Primo David, DENR undersecretary for integrated environmental science and head of

Treñas-Chu slams MPIW over permit delay claims
Iloilo City Mayor Raisa Treñas-Chu criticized Metro Pacific Iloilo Water on Thursday for what she described as the company’s failure to directly raise concerns about alleged delays in the processing of permits for its desalination plant project in Barangay Ingore, La Paz. “I would have appreciated it if MPIW had informed