MONDAY BLACKOUT: Unexplained power outage hits Panay, Guimaras
The National Grid Corporation of the Philippines (NGCP) has yet to fully explain the “system disturbance” that caused the hours-long blackout in Panay and Guimaras islands on Monday, Feb 20, 2023. Based on its 11:24 a.m. advisory, NGCP said it “monitored a system disturbance which affected the entire Panay sub-grid..

By Francis Allan L. Angelo

By Francis Allan L. Angelo
The National Grid Corporation of the Philippines (NGCP) has yet to fully explain the “system disturbance” that caused the hours-long blackout in Panay and Guimaras islands on Monday, Feb 20, 2023.
Based on its 11:24 a.m. advisory, NGCP said it “monitored a system disturbance which affected the entire Panay sub-grid.. “
“NGCP is investigating the root cause of the incident and currently expediting power restoration efforts for affected areas.”
NGCP operates the transmission lines that bring electricity from power plants to distribution utilities and electric cooperatives.
By 2:24 p.m., NGCP said it successfully “restored power transmission services to all affected customers in Panay Island, after the system disturbance monitored at 11:24 AM of the same day.”
“NGCP is awaiting the synchronization of affected power plants back to the grid. Rotating power interruptions may be experienced by customers as supply is currently being sourced from renewable plants.”
NGCP noted that Aklan Electric Cooperative’s franchise area experienced “issues unrelated to the system disturbance.”
Daily Guardian tried to get a more specific explanation on the outage but NGCP only referred to the same advisory on the system disturbance that affected Panay.
The outage heavily affected Iloilo City after its sole power distributor MORE Power lost its supply from the grid.
MORE Power draws its supply from coal-fired power plants owned by Kepco and Sem Calaca, which were operational during the outage. But since NGCP cannot transmit electricity from these plants, city residents and workers had to suffer a sweltering Monday.
The outage also affected nearby Guimaras Island.
In a 6 p.m. advisory, MORE Power said it managed to restore power supply to several feeders in Lapaz, Molo, City Proper, Jaro, Mandurriao and the Megaworld area.
“Please note that additional feeders will be energized as soon as we receive the necessary Mega Watt (MW) from NGCP,” it added.
The unexplained outage occurred on the heels of the 12-hour scheduled brownout that hit parts of Iloilo City over the weekend due to maintenance works by NGCP.
Article Information
Comments (0)
LEAVE A REPLY
No comments yet
Be the first to share your thoughts!
Related Articles
DENR pushes 2027 deadline for new Iloilo bulk water supply
A top official of the Department of Environment and Natural Resources said Iloilo must have a new bulk water supply operational by 2027, warning that the city’s rapid urban growth will further increase water demand in the coming years. Carlos Primo David, DENR undersecretary for integrated environmental science and head of

Treñas-Chu slams MPIW over permit delay claims
Iloilo City Mayor Raisa Treñas-Chu criticized Metro Pacific Iloilo Water on Thursday for what she described as the company’s failure to directly raise concerns about alleged delays in the processing of permits for its desalination plant project in Barangay Ingore, La Paz. “I would have appreciated it if MPIW had informed