Leon engineer cites heavy workload in market project lapses
By Rjay Zuriaga Castor
ILOILO CITY — Leon’s municipal engineer told state auditors that the heavy workload and large volume of projects handled by the engineering office kept it from properly monitoring the town’s PHP 7.27 million public market reconstruction, which its contractor later abandoned.
The explanation is contained in the Commission on Audit’s (COA) 2025 annual audit report on the Municipality of Leon, which faulted the local government for inadequate monitoring and the lack of timely action against the contractor, 1st Rock and Roll Construction Services.
The project, worth PHP 7,267,934.43, was funded by the Iloilo Provincial Government under a memorandum of agreement (MOA) signed on Dec. 27, 2021.
Late start
The MOA required the municipality to implement the project within six months of receiving the funds, which arrived on July 24, 2024.
The municipal engineer told auditors this did not happen because the existing public market had to be demolished before the new project could begin.
The contract took effect on April 26, 2025, and was suspended the same day because demolition of the old covered market was still ongoing, according to COA’s timeline of procurement activities.
A time extension for rainy and unworkable days followed on Dec. 19, 2025, moving the deadline to March 2, 2026.
Slippage spotted late
The engineer said the target schedule and actual accomplishment were not compared when the first and second progress billings were processed, since no negative slippage was noted at that time.
The delay became evident only upon his later assessment, the engineer added.
He determined the negative slippage only on Feb. 24, 2026, after observing that the project was significantly behind its March 2, 2026, deadline.
COA records put actual accomplishment at 51.22% as of Dec. 16, 2025, against a planned 94.10%, a negative slippage of 42.88%.
The municipality released the first progress billing, at 40.50% accomplishment, on Sept. 8, 2025, and the second, at 51.22% accomplishment, on Dec. 29, 2025.
COA said the municipality should have initiated contract termination when the slippage first reached 15%, the threshold set under Government Procurement Policy Board Resolution No. 018-2004 and Presidential Decree 1870.
Accountant, BAC respond
The municipal accountant told auditors that liquidated damages had not been computed because the contract remained under evaluation for possible termination.
The municipality asked the contractor for a catch-up plan on Jan. 20, 2026, prepared a notice to terminate on Feb. 26, 2026, and sent the termination notice through PHLPost on March 23, 2026.
COA noted that the notice went out after the contractor had already abandoned the project.
The contractor’s performance bond expired on March 31, 2026, without being forfeited in favor of the municipality, auditors said.
The chairman of the Bids and Awards Committee (BAC) told auditors that once the contract is terminated, the committee would review the facts and circumstances of the termination and assess the procurement modalities and remedies available under existing laws and rules.
The BAC would then issue a resolution recommending to the head of the procuring entity the most advantageous, appropriate, and legally compliant course of action to continue or complete the project, subject to approval by the proper authority.
What happens next
The municipal mayor agreed to COA’s recommendations, including coordination with the Iloilo Provincial Government on the contractor’s abandonment and compliance with the MOA.
The mayor also agreed to have the BAC evaluate options such as a project takeover, re-procurement, engagement of another qualified contractor, assignment to an adjacent or contiguous contractor, or agency-to-agency implementation under Republic Act No. 12009, or the New Government Procurement Act.
As of September 2026, the Leon LGU had complied with COA’s directives on administrative planning, oversight, and coordination with the provincial government.
At that time, the BAC was preparing the legal and procurement requirements for a project takeover or rebidding to complete the market building.
Comments (0)
LEAVE A REPLY
No comments yet
Be the first to share your thoughts!
Related Articles

500 TABLETS, MORE TO COME: Mayor Raisa leads distribution; secures PHP 500,000 for additional gadgets for Ilonggo learners
ILOILO CITY — More Ilonggo students are expected to gain access to digital learning resources as the Iloilo City Government continues to expand its efforts to equip learners with technology, following the distribution of 500 tablets led by Mayor Raisa S. Treñas. The tablets were distributed to college students and elementary and high school learners

Iloilo eyes province-wide state of calamity as El Niño bites
ILOILO CITY — The Iloilo provincial government is studying a province-wide state of calamity declaration as prolonged dry conditions continue to batter farming communities. Gov. Arthur Defensor Jr. said the decision would depend on whether the province meets the requirements, including the number of local government units that have declared a

DILG: Vice mayors can speak, debate, but not sponsor ordinances
ILOILO CITY — Vice governors and vice mayors, as presiding officers of local legislative councils, cannot sponsor ordinances and may vote only to break a tie, the Department of the Interior and Local Government (DILG) said in a legal advisory. The advisory, however, allows local councils to let presiding officers step