Election ban, utility lines delay PHP 102.8M Lapuz flood project

By Rjay Zuriaga Castor
ILOILO CITY — The Department of Public Works and Highways–Iloilo City District Engineering Office (ICDEO) blamed the Commission on Elections (Comelec) construction ban, utility line obstructions, and bad weather for the nearly yearlong delay of a flood mitigation structure in Barangay Alalasan, Lapuz district.
The construction ban was imposed ahead of the May 2025 midterm elections.
In a written explanation obtained by Daily Guardian, ICDEO said the project has gone through several work suspensions and contract extensions since construction began in February 2025.
The project originally covers 980 linear meters, has a contract cost of PHP 102.798 million, and is being built by F. Gurrea Construction Inc.
According to the DPWH website, the contract took effect on Feb. 20, 2025, and the project was initially scheduled for completion on Jan. 8, 2026.
The website places the project’s physical accomplishment at only 32.14%.
The first delay came shortly after the contract took effect, when construction was suspended pending the issuance of a Certificate of Exemption from Comelec.
The resulting work suspension order covered April 11 to May 25, 2025, and moved the completion date to Feb. 8, 2026.
ICDEO identified existing water pipelines, electrical lines, and telecommunications lines as another major cause of delay, requiring additional coordination and site clearance before construction could proceed.
The obstructions led to a work suspension order covering Aug. 26 to Oct. 9, 2025, which was extended from Oct. 10, 2025, to May 21, 2026.
The agency said it also had to arrange temporary partial road closures with the city government and the DPWH Regional Office 6 in late April 2026.
Construction officially resumed on May 22, 2026, after a work resumption order was issued.
ICDEO said the utility-related disruptions led to more contract extensions, moving the completion target to Nov. 18, 2026.
The agency attributed later delays to persistent rain and unfavorable weather from mid- to late 2026.
March 2027 deadline
After meeting with ICDEO on Nov. 12, Mayor Raisa Treñas-Chu gave the agency until March 2027 to complete the project, rejecting its request for an extension until May 2027.
Treñas-Chu said she had instructed the agency to finish the entire stretch, including the portion extending to Barangay Divinagracia in La Paz, within the new deadline.
“To meet this deadline (March 2027), they need to deploy additional manpower and speed up their work,” she said.
“Because of this delay, some drainage projects of the Iloilo City Government will also have to be temporarily put on hold to ensure proper connectivity between the drainage systems of the local and national government,” she added.
During the meeting, ICDEO committed to building 30 meters of the structure a week on the remaining stretch of about 625 meters.
The remaining work involves excavation, sheet pile driving, installation of precast materials, and concrete pouring.
Treñas-Chu directed ICDEO to submit progress reports every two weeks instead of giving updates only when it requests contract extensions.
She also reminded the agency to strictly enforce construction site safety measures to protect residents and motorists passing through the area.
Treñas-Chu has repeatedly criticized ICDEO projects in the area. On July 27, she blamed ongoing flood control projects in Calubihan, La Paz, and Lapuz for severe flooding brought by southwest monsoon rains enhanced by Tropical Cyclone Kiyapo (international name: Noul).
That flooding displaced 45 families in La Paz and 21 families in Lapuz.
ICDEO projects in the city have been under scrutiny since 2025, when President Ferdinand Marcos Jr. ordered a nationwide investigation into flood control projects and the city government inspected flood control sites in Lapuz and other districts.
Comments (0)
LEAVE A REPLY
No comments yet
Be the first to share your thoughts!
Related Articles

Permanent jobs for barangay workers? Lawmaker says it depends on funds
ILOILO CITY — Making barangay workers’ positions permanent in government remains an ideal goal, but financial constraints continue to stand in the way, Iloilo 3rd District Rep. Lorenz Defensor said on Nov. 16. Defensor recognized the need to give barangay service point officers (BSPOs), barangay health workers (BHWs), day care workers,

‘MINORS ARE NOT CONTENT’: CWC flags radio interview of minor in theft case
ILOILO CITY — The Council for the Welfare of Children (CWC) has urged media practitioners to observe responsible journalism when reporting on children in conflict with the law (CICL) after an Iloilo City-based radio station published online interviews with two minors. In a statement on Monday, the CWC condemned the interview

‘STOP PROMISING, START FUNDING’: 370 million girls sexually assaulted before 18, Plan International warns
More than 370 million girls and women worldwide experienced rape or sexual assault before turning 18, Plan International said Monday, Nov. 16. The group is pressing governments to bring funded and measurable commitments to a global ministerial conference on ending violence against children, set here on Nov. 18 to 19.