COA faults Leon LGU over abandoned PHP 7.27M market project
By Rjay Zuriaga Castor

ILOILO CITY — The reconstruction of the public market in Leon, a town in central Iloilo, remains unfinished after its contractor abandoned the PHP 7.27 million project, with the Commission on Audit (COA) faulting the municipal government for weak monitoring and slow action against the contractor.
In its 2025 annual audit report on the Municipality of Leon, COA said the project was not completed due to inadequate monitoring and the lack of timely remedial action on the contractor’s negative slippage.
As a result, the fund was inefficiently used, the intended benefits for residents were not delivered, and the town lost opportunities for economic growth, auditors said.
The project, worth PHP 7,267,934.43, was funded by the Iloilo Provincial Government through a memorandum of agreement (MOA) with the Municipality of Leon signed on Dec. 27, 2021.
In July 2020, a fire gutted about 100 stalls at the Leon Public Market, Daily Guardian reported at the time.
Under the MOA, the municipality was to implement the reconstruction within six months of the release of the funds, which it received on July 24, 2024.
The municipal engineer told auditors the project did not start within that period because the existing public market had to be demolished first.
The contract was awarded to 1st Rock and Roll Construction Services on March 17, 2025, according to the report.
It took effect on April 26, 2025, with a duration of 240 calendar days and an original completion date of Dec. 22, 2025.
A work suspension due to the ongoing demolition of the old covered market and a time extension for rainy and unworkable days stretched the contract to 310 calendar days, moving the deadline to March 2, 2026.
As of Dec. 16, 2025, the project’s physical accomplishment stood at only 51.22% against a planned 94.10%, a negative slippage of 42.88%.
COA said this level of slippage falls within the terminal stage.
Delayed termination
COA faulted the Leon LGU for failing to initiate contract termination when the project’s negative slippage first reached 15%, the threshold at which Government Procurement Policy Board (GPPB) Resolution No. 018-2004 and Presidential Decree 1870 require a procuring entity to terminate a contract for default.
The same GPPB rules also list a contractor’s abandonment of contract works as a ground for termination.
The municipal engineer documented the negative slippage only on Feb. 24, 2026, less than a week before the revised deadline.
The municipality sent the contractor a letter requiring a catch-up plan on Jan. 20, 2026, and prepared a notice to terminate the contract on Feb. 26, 2026.
The termination notice was sent to the contractor through PHLPost only on March 23, 2026, after the contractor had abandoned the project and a month after the slippage was documented, COA said.
During an ocular inspection on March 12, 2026, auditors found the market still unfinished, 10 days after the revised contract expiry date had lapsed.
Auditors also found that the contractor’s performance bond expired on March 31, 2026, without being forfeited in favor of the municipality.
Meanwhile, the municipal accountant told auditors that liquidated damages had not been computed because the contract remained under evaluation for possible termination.
Records cited by COA show the municipality released the 15% advance payment on July 3, 2025, and the first progress billing, at 40.50% accomplishment, on Sept. 8, 2025.
The second progress billing, at 51.22% accomplishment, followed on Dec. 29, 2025.
“The Municipality’s failure to act promptly made the contractor to continue receiving payments despite clear evidence of non-performance, which exposed public funds to risk and also weakened the enforcement of accountability mechanisms built into government procurement rules,” COA said.
COA relayed its findings to the municipality through Audit Observation Memorandum No. 2026-12 dated April 6, 2026.
Audit recommendations
COA recommended, and the municipal mayor agreed, that concerned personnel coordinate with the Iloilo Provincial Government on the contractor’s abandonment of the project and ensure compliance with the MOA.
Auditors also asked the mayor to ensure that payments are released only after actual accomplishments and compliance with corrective measures are properly validated.
COA also recommended that the municipal engineer and the municipal planning and development officer be instructed to monitor project implementation regularly, report slippage on time, issue written notices to the contractor, and require catch-up programs.
It urged the mayor to have the Bids and Awards Committee (BAC) recommend the best course of action for completing the project, such as a takeover, re-procurement, engagement of another qualified contractor, assignment to an adjacent or contiguous contractor, or agency-to-agency implementation.
These options must follow Republic Act No. 12009, or the New Government Procurement Act, which was signed into law in July 2024.
COA further recommended that the municipal accountant record as receivables from the contractor all costs related to construction deficiencies and defects, and compute the corresponding liquidated damages.
It also called on concerned officials to strictly implement contractual remedies upon termination, including forfeiture of the performance security, retention money, and other guarantees.
Auditors likewise recommended administrative sanctions, such as suspension or blacklisting, against contractors in cases of negative slippage attributable to their fault or willful abandonment of a project.
As of September 2026, the Leon LGU had complied with COA’s directives on administrative planning, oversight, and coordination with the provincial government.
At that time, the BAC was preparing the legal and procurement requirements for a project takeover or rebidding to complete the market building.
The contractor
Public procurement records and corporate documents identify 1st Rock and Roll Construction Services as a construction firm based in Barangay Balabag, Santa Barbara, Iloilo.
The company has also secured infrastructure and repair contracts in Western Visayas, including projects in late 2025 for the Civil Aviation Authority of the Philippines (CAAP) involving the expansion of its CSIS office and emergency repairs to the curtain wall of the passenger terminal building’s public concourse.
Comments (0)
LEAVE A REPLY
No comments yet
Be the first to share your thoughts!
Related Articles

500 TABLETS, MORE TO COME: Mayor Raisa leads distribution; secures PHP 500,000 for additional gadgets for Ilonggo learners
ILOILO CITY — More Ilonggo students are expected to gain access to digital learning resources as the Iloilo City Government continues to expand its efforts to equip learners with technology, following the distribution of 500 tablets led by Mayor Raisa S. Treñas. The tablets were distributed to college students and elementary and high school learners

Iloilo eyes province-wide state of calamity as El Niño bites
ILOILO CITY — The Iloilo provincial government is studying a province-wide state of calamity declaration as prolonged dry conditions continue to batter farming communities. Gov. Arthur Defensor Jr. said the decision would depend on whether the province meets the requirements, including the number of local government units that have declared a

DILG: Vice mayors can speak, debate, but not sponsor ordinances
ILOILO CITY — Vice governors and vice mayors, as presiding officers of local legislative councils, cannot sponsor ordinances and may vote only to break a tie, the Department of the Interior and Local Government (DILG) said in a legal advisory. The advisory, however, allows local councils to let presiding officers step