Another power blackout hits Western Visayas
Another power blackout hit Western Visayas Friday afternoon, causing consternation among consumers who had to go through another day of sweltering weather. In an advisory past 6 pm Friday, the National Grid Corporation of the Philippines (NGCP) said it monitored a system disturbance at 1:50 pm which affected the Visayas grid.

By Rjay Zuriaga Castor

By Rjay Zuriaga Castor
Another power blackout hit Western Visayas Friday afternoon, causing consternation among consumers who had to go through another day of sweltering weather.
In an advisory past 6 pm Friday, the National Grid Corporation of the Philippines (NGCP) said it monitored a system disturbance at 1:50 pm which affected the Visayas grid.
Initial findings show that a distribution utility-owned line tripped and caused power plants to disengage or disconnect from the transmission system.
“An assessment of NGCP’s facilities shows that our protection systems functioned as intended,” it added.
While the initial problem was already addressed and the power supply was restored, another system disturbance occurred at 2:56 pm.
“Initial findings show that the initiating event was the tripping of a generation facility. Similarly, an assessment of NGCP’s protection equipment shows that the transmission system functioned properly,” the firm added.
NGCP manages transmission lines that provide electricity from the power plants to distribution utilities and electric cooperatives.
The blackout again affected the services areas of MORE Power (Iloilo City), the Iloilo Electric Cooperatives I, II, and III (Iloilo province), Aklan Electric Cooperative, Antique Electric Cooperative, Guimaras Electric Cooperative, and parts of Negros Occidental.
NGCP and the power distributors also resorted to load shedding or rotating power interruptions due to low supply.
This is the third region-wide blackout to hit Western Visayas this year. The first was on February 20 and the second on April 27.
Article Information
Comments (0)
LEAVE A REPLY
No comments yet
Be the first to share your thoughts!
Related Articles
DENR pushes 2027 deadline for new Iloilo bulk water supply
A top official of the Department of Environment and Natural Resources said Iloilo must have a new bulk water supply operational by 2027, warning that the city’s rapid urban growth will further increase water demand in the coming years. Carlos Primo David, DENR undersecretary for integrated environmental science and head of

Treñas-Chu slams MPIW over permit delay claims
Iloilo City Mayor Raisa Treñas-Chu criticized Metro Pacific Iloilo Water on Thursday for what she described as the company’s failure to directly raise concerns about alleged delays in the processing of permits for its desalination plant project in Barangay Ingore, La Paz. “I would have appreciated it if MPIW had informed